red brick Indonesia

Sustainable development provides many opportunities for many people. Moreover, supported by rising incomes so as to provide an opportunity to meet the primary needs, such as property. Of this is an emerging opportunity in the procurement of major materials supporting the development of the property is a stone was discovered today bata.Meskipun innovation substitute brick walls of buildings in the making, but most people still use brick.
The results of this effort is the production of brick red brick as a material for the manufacture of building walls, the level of strength and coolness in the manufacture of home is very high when compared with materials that use pressed brick.
Regarding the location of the business has to consider is the location within easy reach of transport and marketing site that allows the creation of broad lolasi place for printing, drying, burning and Shelters Brick Red Brick is ready for market.

A. Preparation Facilities and Equipment.
a. Land elections.
Look for the red soil area in the form of hills / form a hill, and soil texture is clay meranya, which do not contain too much sand, soil bertektur will reduce the strength of the brick.Also close to the water source, as a mixture of red soil.
b. Making buildings / plant.
The size of the building area of
​​± 30M2.
Plant consists of four parts, namely:
1. Stirring and Printing place.
2. Drying place.
3. Combustion place.
4. Bricks gathering place ready for the market.

c. Appliances.
A. Printer engine serves as a mixing ground brick red to a brick clay to tercetaknya

2. Fueling the engine, serves as the driving brick making machine
3. Wooden carts.
4. Carts.
5. Hoe.
6. Shovel.

d. Fuel.
A. Chaff, Coal.
2. Wood.

e. The mixture of materials.
A. Water.
2. Sand.

2. Printing process.

Stages of Printing:
• Land that has been collected in the red flush with water sekupnya.
• Put the red soil with a shovel into the brick making machine.
• Provide on-site discharge miyak brick mold on the machine, so the brick can be printed neatly, what if catakan brick out of the printing press has not been solid or broken, can work diulanggi, by entering the back ground red (brick) into a brick making machines to mold that came out really dense and neat.
• Cut a lengthwise brick mold with cutting tools that are available. In a one-time cuts produce 3 seeds bricks.
• Pick and place or stacking printouts that have been trimmed ketempatnya.Dengan brick making machines and 3 employees in 5000 one day be able to print a brick seed.Fuel used is diesel. Solar is required in the production of 1000 seeds each brick as much as 1 liter.
3. Drying process.
Drying is done until the bricks to dry. This drying takes 5 days non stop, with a record fine weather.
4. The burning process.
• The burning process carried out for 48 hours (2 days) non stop. Every single time there are 100,000 seeds burning brick. The fuel used is a piece of wood, so that long-lasting fuel. Pieces of wood used as much as 2.5 ret tracks.
• If the weather conditions (dry season), the combustion can be done every 20 days. If the weather conditions of the rainy season, the burning can only be done 1 time in 1 month.

5. Red Bricks ready Marketed.
Results in a burning or 70,000 times the seeds are usually bought by the consumer 2 (2 houses). The scope of marketing is a sub-district and district Batulicin Simpang Four.Size for the red brick Length 19cm x Width 9 cm x 5 cm thickness.
ECONOMIC ANALYSIS OF RED BRICK MAKING
Land used for this red-brick making business loans are made, so that at any one time the result of burning the land owner a profit of Rp. 1.000.000, -.
COST OF PREPARATION FACILITY
A. Printer Machine Bata Rp. 40.000.000, -
2. Domping machine Rp. 5,000,000, -
3. Building manufacturing plant and other equipment Rp. 15.000.000, -
Such as:
a. Water Machine
b. Water Drum
d. Wooden carts
e. Hoe
f. Spade
g. And others. . + Number Rp.60.000.000, -

4. Cost Oprasional
A. Land lease (loans made) Rp. 1,000,000, -
2. Employee Wages 70 000 seeds @ Rp. 140, - USD. 9.8 million, -
3. Solar Fuel 70 Liter @ Rp. 6500, - USD. 455 000, -
4. Wood pieces 2.5 Ret @ Rp. 650.000, - Rp. 1.625 million, - +
The amount of Rp. 12.88 million, -
5. Results Marketing.
Brick Sales Price @ USD 70 000 seeds. 450, - USD. 31.5 million, -

Arson First A.Perhitungan Sales Results
• Cost + Fee Facility Oprasional
• Rp. 60 million, - + Rp. 12.88 million, - = Rp. 72.88 million, -.
• The Sales = Rp. 31.5 million, -
Difference = - Rp.41.380.000, -


Arson Second B.Perhitungan Sales Results
• Cost Oprasional = Rp. 12.88 million, -
• Land Charges = Rp. 1,000,000, -
• The Sales = Rp. 31.5 million, -
Difference = Rp. 17.62 million, -

Third Combustion C.Perhitungan Sales Results
Cost Oprasional = Rp. 12.88 million, - Charges Land = Rp. 1,000,000, -
Results Sales = Rp. 31.5 million, -
Difference = Rp. 17.62 million, -

Combustion Fourth D.Perhitungan Sales Results
• Cost Oprasional = Rp. 12.88 million, -
• Land Charges = Rp. 1,000,000, -
• The Sales = Rp. 31.5 million, -
Difference = Rp. 17.62 million, -
• The First Sale = - Rp.41.380.000, -
• The Second Sales = Rp.17.620.000, - +
Difference = - Rp.23.760.000, - +
• The Third Sales = Rp.17.620.000, - +
Difference = - Rp. 6.14 million, - +
• The Fourth Sales = Rp.17.620.000, - +
PROFIT = Rp.11.480.000, -

So in the brick making business, start-up capital will be back after the sale of combustion products into four, with a profit of Rp. 11.48 million, -.

large area and needs an infinite and continuous efforts to make Indonesia the production of bricks in a potential business and no death.
to investors who have a desire to open a business can join me for the development ofred brick.

contact me: 082136946064 Endro




1 komentar:

  1. For all technical help regarding your red brick plant in Indo, pl contact me at : kannan.vk123@gmail.com